Developers and contractors
Building in a perimeter block, excavating next to an old building or driving sheet piles. The record serves as the condition record under § 3(4) VOB/B and as a technical basis for claims under § 909 BGB.
Recording the existing condition (Beweissicherung) before demolition, excavation, piling or repairs: cracks with width, photos with references, a dated report.
Building in a perimeter block, excavating next to an old building or driving sheet piles. The record serves as the condition record under § 3(4) VOB/B and as a technical basis for claims under § 909 BGB.
A construction site is starting next door. The condition of the building is recorded before the first vibrations, whether or not the developer commissions a survey.
Before repairing damage, before acceptance or before building parts are closed up (§ 4(10) VOB/B), the evidence is secured.
A report with instruction, date, attendees, scope, method, findings and the limits of the inspection. It contains a site plan with compass directions, room sketches with numbered walls, and every finding with the same reference in plan, text and photo. Digital and on paper; the final survey compares both conditions.
A condition survey records a condition, not a cause. Causes are established in a separate service. The client organises access to other people's buildings. Liability and compensation are for a lawyer.
Quote with the scope of services on request by email to info@ing-bassam.de.
final survey after completion of the works
up to 6 flats; larger buildings by quote
measurement equipment via specialist firms charged separately
No, there is no right to that. If access is refused, what can be seen from publicly accessible areas is documented and the refusal is recorded in the report.
A condition survey is a private record without a court. Independent evidence proceedings (selbständiges Beweisverfahren) under sections 485 et seq. of the German Code of Civil Procedure (ZPO) are court proceedings with a different procedural effect. Which route suits a situation is a question for a lawyer.
Before the first intervention: before demolition, excavation, shoring, piling or the strip-out after damage. One to two weeks are needed to organise access to neighbouring buildings. Once works have started, the record is of limited use.
It puts it into practice. Section 3(4) VOB/B requires a record of the condition of roads, ground surface and structures in the construction area before work begins. The report is structured so that client and contractor can both sign it.